SP Group Lowers Singapore Household Electricity Tariff By 10.4 Percent For October To December 2026

Singapore’s Q4 tariff shows how Middle East-linked gas price swings pass through to regulated power prices in Southeast Asia.

Thailand’s Oil Fuel Fund Considers 100 Billion Baht Borrowing Facility As Deficit Reaches 92 Billion Baht

The size of the Oil Fuel Fund’s next loan will be set after talks with Thailand’s new energy leadership.

Indonesia’s Energy Ministry Prepares Revision Of PLN Electricity Plan To Accommodate 100 GWp Solar Program

The RUPTL revision will set how Indonesia turns its 100 GWp solar ambition into contracted, grid-connected capacity.

Indonesia’s Energy Ministry Moves To Act On Prabowo Directive To Produce Gasoline From Coal

President Prabowo announced the coal-to-gasoline goal on September 19, and Minister Bahlil confirmed follow-up two days later in Jakarta.
SEND TO: pressreleases@pageonemedia.ph

PLN Bundles 7,046 MW Of Hydropower Projects To Accelerate Indonesia’s RUPTL

Watch Indonesia’s power sector: PLN is testing whether bundled procurement can solve chronic hydropower delays.

PLN Bundles 7,046 MW Of Hydropower Projects To Accelerate Indonesia’s RUPTL

156
156

How do you feel about this story?

Express Your Reaction
Like
Love
Haha
Wow
Sad
Angry

PT PLN (Persero) has moved to bundle hydropower procurement totaling 7,046 megawatts as part of an effort to speed up implementation of Indonesia’s 2025-2034 Electricity Supply Business Plan. The announcement was made by a senior PLN executive at the Indonesia Hydropower Summit 2026 in Jakarta on August 5.

Key Facts At A Glance

  • PLN is bundling hydropower procurement totaling 7,046 MW
  • The move is designed to accelerate Indonesia’s 2025-2034 RUPTL (Electricity Supply Business Plan)
  • The RUPTL calls for 11,689.99 MW of hydropower and mini-hydropower capacity across 315 projects
  • Announcement made by PLN Director of Project Management and New and Renewable Energy Suroso Isnandar
  • Disclosed at the Indonesia Hydropower Summit 2026 in Jakarta
  • PLN says the bundled scheme targets bottlenecks in feasibility studies, licensing, procurement, power purchase agreements, financing, and construction
  • PLN cites grid readiness, regulatory certainty, stable contractual arrangements, and fair risk-sharing as prerequisites for acceleration

PT PLN (Persero), Indonesia’s state-owned electricity utility, said it will bundle hydropower procurement projects totaling 7,046 megawatts to accelerate implementation of the country’s 2025-2034 Electricity Supply Business Plan, known as the RUPTL. PLN Director of Project Management and New and Renewable Energy Suroso Isnandar disclosed the plan on August 5 at the Indonesia Hydropower Summit 2026 in Jakarta.

“The larger the scale, the more competitive the outcome will be,” Suroso said, explaining the rationale behind the bundled procurement approach.

Under the 2025-2034 RUPTL, Indonesia plans to develop 11,689.99 megawatts of hydropower and mini-hydropower capacity through 315 separate projects. PLN said the bundled procurement scheme is intended to address bottlenecks that have historically slowed hydropower development in the country, including delays across feasibility studies, licensing, procurement, power purchase agreement negotiations, financing, and construction.

Suroso said accelerating hydropower development nationally will require adequate grid readiness, regulatory certainty, stable contractual arrangements, and fair risk-sharing between PLN and project developers.

Publicly available details on the specific projects included in the bundle, their locations, and anticipated timelines remain limited, as PLN has not released a project-by-project breakdown alongside this announcement.

EDITORIAL RESEARCH NOTE
This report synthesizes recent reporting and publicly available industry information. The perspectives presented reflect neutral newsroom-style reporting.